12bet online betting

Notice of the Shaanxi Provincial Department of Natural Resources on the issuance of the "Shaanxi Provincial Green 12bet online betting Management Measures"
Time: 2024-04-24 10:41

Natural resources authorities of each city (district):

"Shaanxi Province Green 12bet online betting Management Measures" was reviewed and adopted at the 7th Department Meeting on March 26

Shaanxi Provincial Department of Natural Resources

March 29, 2024

Shaanxi Province Green 12bet online betting Management Measures

Chapter 1 General Provisions

In accordance with the "Mineral Resources Law of the People's Republic of China" and other laws and regulations and relevant documents on green 12bet online betting

Article 2 The 12bet online betting mines referred to in these Measures refer to the entire process of mineral resource development

Article 3 These Measures apply to new construction projects engaged in the development of mineral resources in accordance with the law within the administrative regions of this province

Chapter 2 Green 12bet online betting

The construction of 12bet online betting mines is one of the contents of the exploration and mining information disclosure of mining rights holders

The transfer authority must include green 12bet online betting requirements in the mining rights transfer announcement

Gradually meet the requirements for green 12bet online betting

Article 5 Mining enterprises must establish a 12bet online betting development concept

Article 6 To build green mines, a green 12bet online betting implementation plan (hereinafter referred to as the “implementation plan”) shall be prepared

All new mines and large and medium-sized production mines must comply with industry specifications such as the "Green 12bet online betting Specifications for the Nonferrous Metal Industry" issued by the Ministry of Natural Resources

The mining right holder should submit the implementation plan and electronic documents to the county-level natural resources authority where the 12bet online betting is located for filing

New mines should complete the preparation and filing of implementation plans within one year from the date of obtaining the mining license

County-level natural resources authorities should file the preparation and filing of the implementation plan for the first half of the year before June 20 of each year

The summary of the implementation plan should be published on the enterprise portal website or the website of the county-level natural resources department

A written report and reasons should be submitted to the county-level natural resources authority where the 12bet online betting is located

Chapter 3 Green 12bet online betting Application and Assessment

Article 8 To apply for a green 12bet online betting, the following conditions must be met:

(1) The "Business License", "Mining License" and "Safety Production License" are legal and valid

(2) No administrative penalties have been imposed by the natural resources and ecological environment departments in the past three years

(3) Mining enterprises should publicize exploration and mining information of mining rights holders

And the remaining reserves have a recoverable life of not less than three years

(5) The scope of the mining area does not involve various natural protection areas

(6) Other prerequisites that meet the requirements for green 12bet online betting

Article 9 Green 12bet online betting Application Procedure.

(1) Mining enterprises that have completed green 12bet online betting tasks or met green 12bet online betting requirements should conduct self-assessment

(2) After verification organized by the county-level natural resources department

(3) After review and approval by the municipal natural resources department

(4) Provincial natural resources authorities purchase services from the government

After the provincial natural resources authorities entrusted technical support units to review and organize on-site inspections of some mines

National 12bet online betting mines are recommended from provincial 12bet online betting mines in accordance with relevant requirements

Article 10 The provincial natural resources authorities are responsible for establishing a provincial third-party evaluation agency database for green 12bet online betting

Article 11 Provincial natural resources authorities are responsible for establishing an expert database for green 12bet online betting in the province

Article 12 Application materials.

(1) Green 12bet online betting Declaration Form;

(2) Green 12bet online betting self-assessment report;

(3) Implementation plan reflecting the creation work

(4) Third-party evaluation report;

Review opinions of county-level natural resources authorities

(6) Other information required by the natural resources authorities

(7) Electronic CD-ROM of application materials.

The above application materials must be true and valid

Chapter 4 Supervision and Management

Article 13 The green 12bet online betting directory shall be managed dynamically

(1) The 12bet online betting is closed or bankrupt;

(2) 12bet online betting mines that still fail to meet construction requirements after review and rectification

(3) Illegal mining, especially cross-border mining

(4) Because the mining enterprise was included in the abnormal list of the exploration and mining information publicity system of mining rights holders in our province

(5) Fraudulently passing the green 12bet online betting assessment;

(6) Mines actively apply to withdraw from the list;

(7) It is inappropriate to continue to be included in the list for other reasons.

The natural resources authority at the upper level should regularly conduct supervision and inspection on the promotion of green 12bet online betting at the lower level

Those found to be incompatible with green 12bet online betting standards after on-site inspection but can be rectified within a time limit

Article 15 If a newly built mine fails to perform the green 12bet online betting tasks in the mining rights transfer contract

Article 16 All mining enterprises included in the green mine directory can enjoy mineral resources specified in laws, regulations and documents related to green 12bet online betting

Article 17: Give full play to the bridging and technical support roles of various industry associations

Article 18 12bet online betting mining enterprises should actively accept social supervision

Article 19 Relevant institutions and personnel violate the provisions of these Measures

Chapter 5 Supplementary Provisions

Article 20 These Measures will be implemented from April 30, 2024


Coal transportation e-commerce Coal big data Ordos Coal